At Industrial Air Company, we are currently fully engaged in the realization of a sustainable air treatment system for an advanced paint line. A project where technology, precision, and sustainability come together.
Prefab Production and Testing in Almelo
Over the past few weeks, the installation has been completely prefabricated in our workshop in Almelo. Here, we have also extensively tested the system, ensuring we can work efficiently and with minimal disruption on-site.
On-Site Installation in Full Swing
Last week, we started installing the piping between the cooling machine and the air handling unit in the factory. This week, we placed the new energy-efficient cooling machine in position and continued connecting the piping.
“Thanks to our prefab approach, we can quickly adapt on-site and maintain maximum control over quality and scheduling.”
Ready for Final Testing and Commissioning
Once the piping is fully connected, the installation will be tested again – this time on-site – before it is definitively put into operation. This way, we guarantee a reliable, energy-efficient, and perfectly tuned system that optimally supports the paint line.